Overall Planning
Weekly Planning -Main Tasks
Week 2
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Problem Definition
|
10 hr
|
Package Sorting Systems Research
|
12 hr
|
Package Delivery Research
|
10 hr
|
Rules and Regulations Research
|
8 hr
|
| Create Planning
|
4 hr
|
|
|
|
|
Make Presentation
|
4 hr
|
| Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
| Meeting Thursday
|
4 hr
|
Meeting Thursday
|
4 hr
|
Meeting Thursday
|
4 hr
|
Meeting Thursday
|
4 hr
|
|
|
|
|
|
|
|
Agenda Meeting
|
0.5 hr
|
Week 3
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Product Requirements
|
2 hr
|
External Requirements
|
2 hr
|
Process Requirements
|
2 hr
|
Functional Requirements
|
2 hr
|
|
|
|
|
|
Design Matrix (voor Brainstorm)
|
1 hr
|
Post Weekly Update
|
1 hr
|
| Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
| Brainstorm
|
4 hr
|
Brainstorm
|
4 hr
|
Brainstorm
|
4 hr
|
Brainstorm
|
4 hr
|
| Opening and Transport Concepts
|
10 hr
|
Design Methodologies
|
10 hr
|
Package Retrieval Concepts
|
10 hr
|
Personal Mailbox Concepts
|
10 hr
|
Week 4
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Build Plan Chimney
|
10 hr
|
Package to Cubby System
|
10 hr
|
Test Plan Chimney
|
10 hr
|
Sliding Doors
|
8 hr
|
| Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
Meeting Monday
|
4 hr
|
| Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
| Weekly Update
|
1 hr
|
Fix/Update Design Methodologies
|
2 hr
|
|
|
Planning Update
|
3 hr
|
|
|
|
|
|
|
|
Why We Chose these Concepts
|
2 hr
|
Week 5
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
| Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
| Chimney Build & Test
|
8 hr
|
Package to Cubby
|
10 hr
|
Chimney Build and Test
|
8 hr
|
Sliding Doors
|
6 hr
|
| Chimney Uitwerken
|
4 hr
|
|
|
Cubby to Person
|
4 hr
|
Build Prototype Sliding Door?
|
4 hr?
|
|
|
|
Weekly Update
|
1 hr
|
|
|
|
|
Week 6
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
| Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
| Chimney Concept Afronden
|
6 hr
|
Package to Cubby Afronden
|
6 hr
|
Cubby to Person Afronden
|
6 hr
|
Software Page
|
8 hr
|
| Make mini model of concept
|
4 hr
|
Make mini model of concept
|
4 hr
|
Make mini model of concept
|
4 hr
|
Make mini model of concept
|
4 hr
|
| Legislature Now and Future
|
2 hr
|
Software Page
|
2 hr
|
Weekly Update
|
1 hr
|
|
|
Week 7
| Luc
|
Time
|
Tim
|
Time
|
Frederique
|
Time
|
Karen
|
Time
|
| Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
Meeting Monday
|
2 hr
|
| Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
Meeting Thursday
|
2 hr
|
| Prepare Presentation
|
3 hr
|
Prepare Presentation
|
3 hr
|
Prepare Presentation
|
3 hr
|
Prepare Presentation
|
3 hr
|
| Wiki Clean-up (Page(s) Designation TBD)
|
2 hr
|
Wiki Clean-up (Page(s) Designation TBD)
|
2 hr
|
Wiki Clean-up (Page(s) Designation TBD)
|
2 hr
|
Wiki Clean-up (Page(s) Designation TBD)
|
2 hr
|
| Components/ Working Pages Afronden
|
4 hr
|
Components/ Working Pages Afronden
|
4 hr
|
Components/ Working Pages Afronden
|
4 hr
|
Components/ Working Pages Afronden
|
4 hr
|
| Legistlature Now & Future (USE)
|
2 hr
|
Weekly Update
|
1 hr
|
USE Aspect (TBD)
|
4 hr
|
Whole System/Multi-Functionality Explanation of Design
|
3 hr
|
Milestones
| Date/Week
|
Milestone/Deliverable
|
| 17 Sept - Deliverable
|
Requirements complete and online
|
| 18 Sept
|
Brainstorm Session
|
| 22 Sept - Deliverable
|
Concepts Chosen & Further Task Division Decided
|
| 29 Sept - Deliverable
|
Build & Test Plan for Chimney Done
|
| 6 October
|
Testing of Chimney Complete (Hopefully)
|
| 13 Oct - Deliverable
|
Chimney, Sliding Doors, Chimney to Cubby, Cubby to Person & Software Completely Finished
|
| 16 Oct
|
Wiki Pages up to date & thorough complete (minus Kinks)
|
| 18 Oct
|
Presentation & Wiki Complete & Ready
|
| 20 Oct - Deliverable
|
Deliver Presentation
|
Deliverables * Deadlines
Milestones
| Done
|
Due Date
|
Milestone
|
Description of task
|
| X
|
|
Milestone 1
|
Description here
|
|
|
|
Milestone 2
|
Description here
|
|
|
|
Milestone 3
|
Description here
|
|
|
|
Milestone 4
|
Description here
|
|
|
|
Milestone 5
|
Description here
|