Planning & Milestones: Difference between revisions

From Control Systems Technology Group
Jump to navigation Jump to search
 
(21 intermediate revisions by 2 users not shown)
Line 1: Line 1:
After week 3 or so we redid the planning so that it would be clear what we wanted to achieve with our project. Below you find divided tasks, an overall overview and milestones.
<br>
Click here to see the [[Old Planning]].
Click here to see the [[Old Planning]].
{| border="1" cellpadding="5" cellspacing="0" align="right" width="40%"
{| border="1" cellpadding="5" cellspacing="0" align="right" width="40%"
|+ '''Quick Links'''
|+ '''Quick Links'''
Line 8: Line 11:
| [[PRE_Groep1| Home]]  
| [[PRE_Groep1| Home]]  
| [[Problem Definition]]
| [[Problem Definition]]
| [[Sliding Doors]]
| [[Opening]]
| &nbsp;
| [[Scenarios]]
|-
|-
| [[Planning & Milestones|Planning and Milestones]]
| [[Planning & Milestones|Planning and Milestones]]
| [[Background Research]]
| [[Background Research]]
| [[Chimney]]
| [[Chimney]]
| &nbsp;
| [[Rules & Regulations]]
|-
|-
| [[Meetings]]
| [[Meetings]]
| [[Requirements]]
| [[Requirements]]
| [[Chimney to Cubby]]
| [[Chimney to Cubby]]
| &nbsp;
|  
|-
|-
| [[Design Methodology| Design Method(s)]]
| [[Design Methodology| Design Method(s)]]
Line 26: Line 29:
| &nbsp;
| &nbsp;
|-
|-
|style="border-bottom: 3px solid grey;" | [[Personal Logs]]
| [[Personal Logs]]
|style="border-bottom: 3px solid grey;" | [[Concepts Chosen]]
| [[Concepts Chosen]]
|style="border-bottom: 3px solid grey;" | Software
| [[Software]]
|
|-
|style="border-bottom: 3px solid grey;" | [[Peer Review & Reflection]]
|style="border-bottom: 3px solid grey;" |  
|style="border-bottom: 3px solid grey;" | [[The Whole Drone Package System Concept| Whole System]]
|style="border-bottom: 3px solid grey;" | &nbsp;
|style="border-bottom: 3px solid grey;" | &nbsp;
|}
|}


= Overall Planning =
= Overall Planning =
[[File:Group1- New Gaunt Planning Project Robot.png|center|x600px]]


= Weekly Planning -Main Tasks =
= Weekly Planning -Main Tasks =


==Week 2==
==Week 2 (Sept 9-15) ==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 93: Line 104:
| 0.5 hr
| 0.5 hr
|}
|}
==Week 3 ==
==Week 3 (Sept 16-22) ==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 150: Line 161:
| 10 hr
| 10 hr
|}
|}
==Week 4 ==
==Week 4 (Sept 23-29)==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 162: Line 173:
! Time
! Time
|- valign="top"
|- valign="top"
| scope="row" | Build Plan Chimney
| scope="row" | Chimney
| 10 hr
| 10 hr
| Package to Cubby System
| Package to Cubby System
| 10 hr
| 10 hr
| Test Plan Chimney
| Chimney / Cubby to Person System
| 10 hr
| 10 hr
| Sliding Doors
| Sliding Doors
Line 207: Line 218:
| 2 hr
| 2 hr
|}
|}
==Week 5 ==
 
At first we had put two people on the chimney system for a build and test plan Idea, however since we changed to a lift mechanism everyone received their own component to elaborate on.
 
==Week 5 (Sept 30 - Oct 6) ==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 237: Line 251:
| 2 hr
| 2 hr
|- valign="top" scope="row"  
|- valign="top" scope="row"  
| Chimney Build & Test
| Chimney  
| 8 hr
| 10 hr
| Package to Cubby
| Package to Cubby
| 10 hr
| 10 hr
| Chimney Build and Test
| Cubby to Person
| 8 hr
| 10 hr
| Sliding Doors
| Sliding Doors
| 6 hr
| 6 hr
|- valign="top"
|- valign="top"
| scope="row" | Chimney Uitwerken
| scope="row" | Build Protype Chimney?
| 4 hr
| 4 hr?
|
|
|  
|  
|  
|  
| Cubby to Person
| 4 hr
| Build Prototype Sliding Door?  
| Build Prototype Sliding Door?  
| 4 hr?
| 4 hr?
Line 264: Line 278:
|
|
|}
|}
==Week 6 ==
 
==Week 6 (Oct 7 - 13)==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 303: Line 318:
| 8 hr
| 8 hr
|- valign="top"
|- valign="top"
| scope="row" | Make mini model of concept
| scope="row" | Legislature Now and Future
| 4 hr
| 4 hr
| Make mini model of concept
| Software Page
| 4 hr
| 4 hr
| Make mini model of concept
| 4 hr
| Make mini model of concept
| 4 hr
|- valign="top"
| scope="row" |  Legislature Now and Future
| 2 hr
| Software Page
| 2 hr
| Weekly Update
| Weekly Update
| 1 hr
| 1 hr
Line 321: Line 327:
|  
|  
|}
|}
==Week 7 ==
 
==Week 7 (Oct 14-19)==
{| border="1" class="wikitable" cellpadding="2" width="100%"
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
Line 388: Line 395:
|}
|}


= Milestones =
= Milestones,  Deliverable & Deadlines=
{| border="1" class="wikitable" cellpadding="2" width="75%"
{| border="1" class="wikitable" cellpadding="2" width="80%"
|- valign="top"
|- valign="top"
! Completion
! scope="row"  width="25%" | Date/Week
! scope="row"  width="25%" | Date/Week
! width="75%" | Milestone
! width="75%" | Milestone/Deliverable
|- valign="top"
|- valign="top"
| scope="row" | 22 Sept
| style="background-color:#20ff74;" |
| Concepts Chosen & Further Task Division Decided
| scope="row" | 15 Sept - Deliverable
|}
| [[Background Research]] online
 
|- valign="top"
= Deliverables * Deadlines =
|style="background-color:#20ff74;" |
=Milestones=
| scope="row" | 17 Sept - Deliverable
 
| [[Requirements]] & Matrix complete & online
{| border="1" class="wikitable" cellpadding="2" width="100%"
|- valign="top"
|- valign="top"
! scope="row"  width="5%" | Done
|style="background-color:#20ff74;" |
! width="10%" | Due Date
| scope="row" | 18 Sept
! width="20%" | Milestone
| Brainstorm Session
! width="65%" | Description of task
|- valign="top"
|- valign="top"
! scope="row" | X
|style="background-color:#20ff74;" |
| <!--Insert Date here -->
| scope="row" | 22 Sept - Deliverable
| Milestone 1
| [[Concepts Chosen]] & Further Task Division Decided
| Description here
|- valign="top"
|- valign="top"
! scope="row" | <!--X here is complete-->
|style="background-color:#20ff74;" |
| <!--Insert Date here -->
| scope="row" | 13 Oct - Deliverable
| Milestone 2
| [[Chimney]], [[Opening]], [[Chimney to Cubby]], [[Cubby to Person]] & [[Software]]  Finished
| Description here
|- valign="top"
|- valign="top"
! scope="row" | <!--X here is complete-->
| style="background-color:#20ff74;" |
| <!--Insert Date here -->
| scope="row" | 16 Oct
| Milestone 3
| Wiki Pages up to date & thorough complete (minus Kinks)
| Description here
|- valign="top"
|- valign="top"
! scope="row" | <!--X here is complete-->
|style="background-color:#20ff74;" |
| <!--Insert Date here -->
| scope="row" | 18 Oct
| Milestone 4
| Presentation & Wiki Complete & Ready
| Description here
|- valign="top"
|- valign="top"
! scope="row" | <!--X here is complete-->
|style="background-color:#20ff74;"|
| <!--Insert Date here -->
| scope="row" | 20 Oct - Deliverable
| Milestone 5
| Deliver Presentation
| Description here
|}
|}

Latest revision as of 20:09, 19 October 2014

After week 3 or so we redid the planning so that it would be clear what we wanted to achieve with our project. Below you find divided tasks, an overall overview and milestones.
Click here to see the Old Planning.

Quick Links
Project Trajectory Project Pages
Home Problem Definition Opening Scenarios
Planning and Milestones Background Research Chimney Rules & Regulations
Meetings Requirements Chimney to Cubby
Design Method(s) Brainstorm Cubby to Person  
Personal Logs Concepts Chosen Software
Peer Review & Reflection Whole System  


Overall Planning

Group1- New Gaunt Planning Project Robot.png

Weekly Planning -Main Tasks

Week 2 (Sept 9-15)

Luc Time Tim Time Frederique Time Karen Time
Problem Definition 10 hr Package Sorting Systems Research 12 hr Package Delivery Research 10 hr Rules and Regulations Research 8 hr
Create Planning 4 hr Make Presentation 4 hr
Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr
Meeting Thursday 4 hr Meeting Thursday 4 hr Meeting Thursday 4 hr Meeting Thursday 4 hr
Agenda Meeting 0.5 hr

Week 3 (Sept 16-22)

Luc Time Tim Time Frederique Time Karen Time
Product Requirements 2 hr External Requirements 2 hr Process Requirements 2 hr Functional Requirements 2 hr
Design Matrix (voor Brainstorm) 1 hr Post Weekly Update 1 hr
Meeting Monday 4 hr Meeting Monday 4 hr Meeting Monday 4 hr Meeting Monday 4 hr
Brainstorm 4 hr Brainstorm 4 hr Brainstorm 4 hr Brainstorm 4 hr
Opening and Transport Concepts 10 hr Design Methodologies 10 hr Package Retrieval Concepts 10 hr Personal Mailbox Concepts 10 hr

Week 4 (Sept 23-29)

Luc Time Tim Time Frederique Time Karen Time
Chimney 10 hr Package to Cubby System 10 hr Chimney / Cubby to Person System 10 hr Sliding Doors 8 hr
Meeting Monday 4 hr Meeting Monday 4 hr Meeting Monday 4 hr Meeting Monday 4 hr
Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr
Weekly Update 1 hr Fix/Update Design Methodologies 2 hr Planning Update 3 hr
Why We Chose these Concepts 2 hr

At first we had put two people on the chimney system for a build and test plan Idea, however since we changed to a lift mechanism everyone received their own component to elaborate on.

Week 5 (Sept 30 - Oct 6)

Luc Time Tim Time Frederique Time Karen Time
Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr
Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr
Chimney 10 hr Package to Cubby 10 hr Cubby to Person 10 hr Sliding Doors 6 hr
Build Protype Chimney? 4 hr? Build Prototype Sliding Door? 4 hr?
Weekly Update 1 hr

Week 6 (Oct 7 - 13)

Luc Time Tim Time Frederique Time Karen Time
Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr
Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr
Chimney Concept Afronden 6 hr Package to Cubby Afronden 6 hr Cubby to Person Afronden 6 hr Software Page 8 hr
Legislature Now and Future 4 hr Software Page 4 hr Weekly Update 1 hr

Week 7 (Oct 14-19)

Luc Time Tim Time Frederique Time Karen Time
Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr Meeting Monday 2 hr
Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr Meeting Thursday 2 hr
Prepare Presentation 3 hr Prepare Presentation 3 hr Prepare Presentation 3 hr Prepare Presentation 3 hr
Wiki Clean-up (Page(s) Designation TBD) 2 hr Wiki Clean-up (Page(s) Designation TBD) 2 hr Wiki Clean-up (Page(s) Designation TBD) 2 hr Wiki Clean-up (Page(s) Designation TBD) 2 hr
Components/ Working Pages Afronden 4 hr Components/ Working Pages Afronden 4 hr Components/ Working Pages Afronden 4 hr Components/ Working Pages Afronden 4 hr
Legistlature Now & Future (USE) 2 hr Weekly Update 1 hr USE Aspect (TBD) 4 hr Whole System/Multi-Functionality Explanation of Design 3 hr

Milestones, Deliverable & Deadlines

Completion Date/Week Milestone/Deliverable
15 Sept - Deliverable Background Research online
17 Sept - Deliverable Requirements & Matrix complete & online
18 Sept Brainstorm Session
22 Sept - Deliverable Concepts Chosen & Further Task Division Decided
13 Oct - Deliverable Chimney, Opening, Chimney to Cubby, Cubby to Person & Software Finished
16 Oct Wiki Pages up to date & thorough complete (minus Kinks)
18 Oct Presentation & Wiki Complete & Ready
20 Oct - Deliverable Deliver Presentation