Introduction

The ring of Eindhoven

Every day a lot of people are waiting before a traffic light some point in their drive. This can causes frustration for the drivers, and more pollution for the environment. After all, driving the same speed continuously is a lot less intensive than stopping and then go again. So, it would be quite optimal if these drivers can continue driving past these traffic lights. Obviously, this is not possible for all traffic lights in the world, however, there are quite some traffic trajects where this could certainly be improved. A continuously connected traffic road, for instance a ring around a city, is a good example. For this reason the project took as basis to improve the ring around Eindhoven, a city in the Netherlands.

One of the methods to improve traffic flow is through the use of green waving. Here cars can continuously get a serie of green lights when they drive at an appropriate speed. For this project it was decided to try to implement green waving in a ring system. This was modelled through the use of the program Netlogo, where eventually a ring of twelve crossings was achieved. The algorithm of the individual traffic lights were based on a previous group’s work in order to eventually create an even better system. In order to register the presence of a car in front of a light the efficiency difference between chips in the cars themselves and sensors directly build into the traffic system itself was researched during the literature studies. To connect as it were all the traffic lights into one overreaching system for the green waving effect, a periodic time interval reminiscent of a clock was introduced. This can trigger the start of a green wave on the ring. From the results it could be concluded that the new system was indeed better on some improvement points in comparison to the reference traffic system.

Authors

  • 0960493 Tim Houthuijs
  • 0934016 Kevin Jenniskens
  • 0958509 Matthijs van Raaij
  • 0948190 Sarah Rohder
  • 0903327 Floris Tulner
  • 0945501 Lars Verstraelen

Focus, Objectives and Approach

The goal of this project is to ultimately improve the traffic system which consists of several crossings by trying to add functionality to the individual traffic lights crossings to smartly create and use green waves. The new system tries to use this through the use of a time based order, similar to the path of a clock hand. In order to make sure that the new system compared to the old system is indeed better, it gets compared on five different variables:

  • The average time it takes for an individual to drive to its destination
  • How often a car has to stop during their trip
  • How long a car has to stop when stopped
  • How long a car has to stop on average for all cars
  • The throughput of the system: How many cars pass the system within a set amount of time

These variables should lead to be able to answer the main question: Is the new system an improvement over the old traffic system?

Additionally, to answer this particular question, it has been divided into different sub-questions, which will ultimately lead to the conclusion to the final main question. The following sub-questions has been deemed interesting to answer:

  • How does the old system work?
    • How does the system take its different users into account?
  • How does the old system work for more intersections?
  • What exactly is a green wave?
    • What exactly is the purpose of creating a green wave?
  • What sensors are needed for this to work in the traffic system?

Focus

Requirements

  • The traffic system is a ring
  • 2-lane road, with near traffic lights left and right turn lanes
  • Sensors in road around traffic lights to detect cars
    • Speed and location of the cars can measured

Preferences

  • Using green waving as much as possible
  • The simulation needs to be as realistic as possible
  • The spawning of the cars in the simulation needs to represent by realistic distribution

Constraints

  • Cars cannot wait too long
  • Emergency vehicles will not be simulated
  • Each traffic light needs to make an estimation to determine the next traffic light state. This can be done with the Cost function of the previous group or an upgraded version of this.

Assumptions

  • Cars do not drive through red
  • All vehicles will stay below speed limitations

Approach

The project needed to be divided into several milestones:

  • The old traffic system that was to be used as baseline needed to compare the new traffic system to needs to be extended to include more than one intersection.
  • A first simple system using the new ‘clock’ based algorithm needs to be implemented.
  • The simple system needs to be extended to a more advanced system, which is more realistic like.
  • For every milestone background information and other relevant knowledge needs to be found, in order to successfully fulfil every milestone. A milestone should be completed before work on the following milestone can begin, however, in reality a lot of the background information and such will happen in parallel.

USE aspects

The situation that is developed in this Wiki is reminiscent of a situation that can be found in real life. Obviously, it is a simplified model of such a real life situation, but suitable for this project. However, even if the model is simplified, the different aspects of the real life equivalent should not be ignored. For instance, the role of the pedestrians that can be found trying to cross the ring are practically reduced to the assumption that that only happens when the light is red for the automobiles. However, to just ignore a such significant user of the traffic system in the Netherlands is quite brash. Thus, in this section the different USE aspects that are important to the specific simplified model of this project will be discussed, but also those in a similar real life situation, where the stakeholders should be the same.

Users

The users of the traffic system in the Netherlands consist of everyone participating in traffic. This ranges from users on wheels, such as automobiles and lorries, to pedestrians and cyclists. Even within these user groups there are different preferences and wishes to how the traffic system should look like. For instance, automobilists want to drive as fast as possible, while never having to stop for something else. Pedestrians want to safely walk alongside the faster traffic, such on curbs, and be able to cross the road where they need to. Obviously, this contradicts each other in a way. So, an overview of these different groups need to be made, such as can be seen in the list below.

Car Owners

  • Drive as fast as possible
  • Nothing that slows down or stops their journey (such as traffic lights)
  • If there is a waiting time, let it be as short as possible
  • Good quality roads
  • To pay as less as possible on fuel
  • Everybody keeps to the traffic rules

Pedestrians

  • Safe place to walk
  • Safe place to cross the road
  • If there is a waiting time, let it be as short as possible
  • Everybody keeps to the traffic rules

Cyclists

  • Safe place to cycle
  • Wants to cycle as fast as it can
  • Nothing to slow down or stop their journey
  • If there is a waiting time, let it be as short as possible
  • Good quality roads
  • Everybody keeps to the traffic rules

Special types of vehicles (ambulances, fire trucks)

  • Being able to pass regular traffic in an emergency in a safe way
  • Travelling time as short as possible
  • Always green lights for any traffic light

Unfortunately, not all of these wishes can be granted, nor can all wishes be considered in this projects simplified model. For instance, a constraint of the model is that special vehicles, pedestrians, and cyclist will not be modeled into the system. Pedestrians and cyclist will be present, they will just not be separately simulated, as the assumption is that when the light is red for the ring users, then those two groups can safely cross the ring. Furthermore, since the simulation is based around optimising a traffic light-based system, it is difficult to grant the wish to all users that they never have to stop during their journey. However, the goal of this project is to try to optimise the waiting time, making it as short as possible for all present users. Additionally, this should also create a safer traffic environment for all involved, granting at least a few of the wishes of every user.

Society

The next important stakeholder in the ring-based traffic system is Society itself. Society also consists of the previous mentioned users, but also users that do not participate (at the moment) in the traffic system, thus keeping their wishes in mind as well. Furthermore, Society also has different interests and smaller stakeholders within, such as the environment, the economy, and ranking compared to other Societies (such as in a different country). An overview of the wishes in the Society needs be made, but it also needs to be clear what kind of different groups are represented in this projects Society,

Environment

  • The CO2 emission should be lowered
  • There should be less pollution
  • No destroying the environment
  • Society needs to be green, and look/see green (think planting trees and such)

Economy

  • The quality of the traffic system should be at a minimum level, preferably higher
  • Any change to the traffic system should be as cheap as possible
  • Everybody needs to be able to reach their destination as fast as possible, since any delay costs *money

Compared to other Societies

  • This Society needs to be the greenest
  • It needs to have the safest roads
  • It needs to have the highest quality of roads

Other User groups

  • The roads need to be as safe as possible
  • The roads need to be clean (think, no garbage from cars and such)
  • The traffic should preferably be as far away from Society as possible

As can be seen, there are quite a few wide ranging wishes coming from Society. Some, such as the wish to have the highest quality of road material to be used in the roads are not relevant to this project in that it will not be simulated. However, the wish to make changes to the existing traffic system as low-cost as possible, and of course preferably even zero, is quite interesting. It will not be necessarily simulated or the goal of this project, but if the traffic system can be optimised using the concepts within this project without or barely changing the existing traffic system, then that would be quite a feat.

Enterprise

The last type of stakeholder are the entrepreneurs they are just as important to the traffic system as the User and Society stakeholders. The main stakeholders are the following:

  • Car Manufacturers
    • they want to make as much money as possible
    • they want their product to be the most user friendly
  • Oil companies
    • They want to sell their oil for the highest rate
    • They want cars to use much oil so they can sell more
    • They do not want cars to be energy sufficient
  • Garages
    • They want to create trust between their customers
    • They want cars to be more fragile
  • (GPS-manufactures)
  • (Sensor-manufactures)

Car Manufacturers

Car manufactures like BMW, Audi, Kia, Tesla, and more all make new cars with new technology in them. One of these technologies is camera’s and park sensors, most new produced cars have them. These sensors can also be used to the to measure the distance between two cars. Some companies even use these kind of sensors to make the car semi self driving. These semi self driving cars have adaptive cruise control which works like a normal cruise control but now the car slows down when it comes to close to another car. This technology can be used to form a platoon. As we draw down to a conclusion it can be concluded that car manufacturers show their interest in these more autonomous kind of cars. To make sure their product stays top of the business.

The companies that will design and build the autonomous cars for instance, or the ones that will build any new updated traffic system will have quite an interest in an improved traffic system.

Literature research

For a project to be successful, research needs to be done. It is important to know what needs to be researched, which in this case includes information on how traffic lights gather information and how autonomous cars gather information.

Information gathering of traffic lights

History green waves

A green wave is implemented mostly in big cities to provide a more efficient traffic flow. This green wave is generated through sending a signal through successive traffic lights, so when traffic is about to pass by, the light will be turned to green. Note that a green wave will only head in one direction on a continuous road. Green waves are a solution to still retain a stable traffic flow, which allows for the cars on the road to not wait too long to drive further. One of the first reported cases of the use of the term ‘’Green Wave’’, was already in the 1960s in Germany. Here the German Federal Railway utilized an advertising campaign where the proposition of a green wave was made. This was made by handing out the possibility to traverse the speed and open track blocks to their travelers, so they could choose between traveling by use of the railways or by car. Moving way further into time, Green waves were in the 2000s first implemented in big cities like San Fransisco [1], where the first both lane Green wave was introduced for cyclists.

Protest on Green waves

The late 2000s were also times of debate surrounding around green waves. These waves would result in a reduction of cars stopping, and thus a reduction in leaving from a stop-position. Leaving from stop is a fuel consuming task for the car. So the protest was coming from the Department from Transport, who stated that it would be bad for the sale of gasoline. [2] Because of the fact that gasoline has a piece of its price being tax, it would be a loss of revenue for tax funds and the government. Over the years this debate has been silenced and also made vague, so it’s not sure whether this discussion is still taking place.

Sensors

Something that has to be taken into account, is the way the traffic lights have to interact or gain information from the moving vehicles. This means that there has to be a device which can communicate to the traffic light. Some ways of achieving this, might be to have a chip that interacts between the cars and the traffic lights, which may provide information both ends of the communication-cycle. However, the GPS chips at the time are not well-equipped for handling situations such as Eindhoven, as it is a big city.[3] The focus of this project lies on the present day, so this limits the choice.

As the non-autonomous cars cannot be interacted with via signaling or other means of digital communication, it being a humanly driven vehicle, the requirements the device should have, can be reduced to it just scanning the environment. This can be done via sensors that exist in the world of today, but also in other ways. This includes ways such as a ultrasonic sensor system, image sensor system or the far infrared sensor system. Each of these has its perks and downfalls, but the image sensor system, while being least efficient on power usage, has the ability to check for the velocities of vehicles and the length of a jam, aside from just the number of vehicles and the occupancy, along with being able to check multiple lanes at once.[4] One of the main subjects that is to be implemented and researched in this project, is the efficiency in terms of velocity, CO2 emission and more. As such, the most reliable way of scanning the environment in front of a traffic light, is the image sensor system.

The current system used in the Netherlands is by ways of a metallic sensor, that detects if a certain mass has been reached before allowing the detected object to be seen as a vehicle. This is not sufficient in terms of checking for velocity, or other important matters that need to be determined.

Information gathering of autonomous cars

Before implementing autonomous cars into the model and ultimately the real world, some background information is needed. So what are now a day cars capable to send and receive from the world ? To do so Tesla's autopilot was considered the best option since it is modern and gives a lot of open information. Unlike the WAYMO project of google. So what makes it possible that the Tesla model s , x and 3 all have semi-autonomous driving? The answer to that is sensors and a computer. All the Tesla’s are equipped with 8 different sensors: rear facing side cameras , front facing overview camera , main front facing camera , front facing distance camera , camera to drive backwards , ultrasonic system , front facing side cameras and radar. These sensors have the following properties:

  • rear facing side cameras
    • max range of 100 meters [5]
    • keep track of the blind spots
    • is used to safely switch lanes
  • Front facing overview camera
    • max range is 60 meter [5]
    • a 150 degree view [6] detects traffic light signs and obstacles that are on the route the vehicle is taking
  • Main front facing camera
    • max range is 150 meters [5]
    • is mainly used to stay in lane and detect obstacles
  • front facing distance camera
    • max range is 250 meters
    • this camera is handy when driving at high speed to spot a difference in environment ahead.
  • camera to drive backwards

Algorithm

Contemporary traffic light algorithm

Currently a very standard model is being used for the structuring of traffic. 90% of the traffic lights (in big cities as well as small villages) work as follows: when a car approaches a traffic light, it is either green or red. When it turned red, the traffic light waits for the traffic lights in the area to either turn red or to accommodate to a situation in which both this traffic light as well as the others can work. Then it will turn green with an initial green time. When no more traffic is passing through, the light will turn to red in less time than the green time was supposed to last. If traffic is passing continuously, then the green light will turn red after the green time has passed.

Algorithm by previous group

PRE2016 1 group 2 was a group of students who were already working on creating on a new traffic system at intersections. This group didn’t necessarily concentrate on a system where lights are turned green or red when a car is waiting in front of it. They instead made a system in which the greentime and the moments when a light is turned green, is dependent off of the amount of cars that are waiting in front of the traffic light.

Content of Algorithm

In this chapter the contents of the algorithm will be explained in more detail.

States

To turn this system into a practise, the previous group first defined all state (in there case 18) that are possible. With a state is meant the combination of red and green lights at the intersection at a certain time. These state are:

  • All pedestrians green, all car lights red;
  • 4 rotations of one right turn car lane green, 2 pedestrian routes green;
  • 4 rotations of two right turn car lane green, 1 pedestrian route green;
  • All right turn car lanes green, all pedestrians red;
  • 4 rotations of one left and straight car lane green, one right turn lane green and one pedestrian route green;
  • 4 rotations of one left and straight car lane green, two right turn lanes green and all pedestrian routes red.

Of course this are not all states available but these are the states where no other light can’t be added without causing an accident.

Cost function

For each of the state the cost will be calculate by the costfunction. This cost function was defined which determined whether a light has a priority on other lights to turn green. This function is defined as follows for the car lanes:

  • Cost_Lane = Cost_traffic + Cost_waittime + Cost_waitlimit = N + B + C_1 * t + P * e_1(t) ;

And for the pedestrians:

  • Cost_Pedestrianlane = Cost_waittime + Cost_waitlimit = C_2 * t + P * e_2(t);

Here are:

  • C(t,N,B): The total cost dependent off of the amount of both non-autonomous vehicles and vehicles with human drivers as well as the waiting time;
  • N: The amount of autonomous vehicles. The traffic system get this amount through communication with the autonomous vehicle.;
  • B: the number of normal cars in the turn lane as reported by the autonomous cars (R is smaller or equal to the total number of normal cars in the turn lane).;
  • C_1: The constant to provide the severity of the waiting time in front of a traffic light;
  • t: The waiting time;
  • P: A large value (in the order of thousands);
  • e_1(t): A function switching to 0 if t < T_maxcar and to 1 if t > T_maxcar;
    • T_max: the maximum time a vehicle can be expected to wait at a intersection;
  • e_2(t): A function switching to 0 if t < T_maxpedestrian and to 1 if t > T_maxpedestrian;
    • T_maxpedestrian: the maximum time a pedestrian can be expected to wait at a intersection;

So the bottom line of this function is: a green light is provided to the biggest row of cars in combination with their waiting time. This function is implemented in each traffic light at the intersection.

Algorithm in simulation

Packet loss

Due to the fact that the algorithm counts the amount of cars by communicating with the autonomous vehicles on the road, there is a chance that error in the communication. There for a packet loss was implemented in the simulation. This needed to make the simulation more realistic.

Spawning of Cars

In simulation the algorithm was implemented no real traffic data was used. The spawn time of new vehicles was composed out of three components: a base time that defines the minimum time between vehicles, a slider dependent time that allows the user of the simulation to determine the number of vehicles that arrive at the intersection and a random number, because vehicles arrive at an intersection in an unpredictable manner, or at least one should not assume it is predictable. This random number is a Gaussian distributed random variable.

Green wave

A Green Wave effect with several intersection wasn’t implemented in the simulation. However, a Green Wave like effect can be used in another way by just the one intersection that the autonomous vehicle is approaching. The car will receive an estimation of what state the intersection will be in when it arrives at the intersection. This method was used in the simulation.

The new Algorithm

The clock system

The amount of states in the system is improved upon by adding multiple more states to the system. The new system makes use of the proposed sensors in chapter 5.1 to detect all cars in front of the traffic lights, instead of only using autonomous cars to detect the cars around them, which also make communication errors. For the traffic light system a new algorithm was imagined where all traffic lights are connected to a “clock system” as described in chapter 6. This clock system is integrated into the cost function for the states where the people on the ring can drive. This makes the clock system not 100% effective in creating green waves but it will increase the cost of the states to try and keep a green wave in effect. The system should in theory improve the efficiency of the system by allowing the cars on the ring, which have further to travel, to have more chance to be driven on.

Content of Algorithm

In this chapter the contents of the algorithm will be explained in more detail.

States

In the new algorithm all possible states are still included. Due to the difference in simulation the amount of state also changes. This change comes due the fact that the previous group just one lane for going forward and left. Well the new simulation uses two different lanes. The new states are:

  • All pedestrians green, all car lights red;
  • 4 rotations of one right turn car lane green ,one right turn lane green and 2 pedestrian routes green;
  • 4 rotations of two right turn car lanes green, one straight car lane green, 1 pedestrian routes green;
  • All right turn car lanes green;
  • 2 rotations of two right turn car lanes green and two straight car lanes green;
  • 4 rotations of three right turn car lanes green and one straight car lanes green;
  • 4 rotations of two right turn car lanes green, one left turn car lane and one straight car lane green;
  • 4 rotations of three right turn car lanes green and one left turn car lane green;
  • 4 rotations of one left and straight car lane green, one right turn lane green and one pedestrian route green;
  • 4 rotations of two straight car lanes green, one right turn car lane green and one pedestrian route green;
  • 2 rotations of two straight car lanes green and 2 pedestrian routes green;

Clock

The system that we are looking into, is mainly targeted to be used on rings of big cities. To describe this idea, an analogy with a clock is being proposed: a clock has a cursor which turns around its own axis. This pointer slides along the circumference of the clock. One can imagine the end of this cursor to be a car, which passes over a road with a constant speed. This is what we assume of a green wave: a state in which cars are allowed to pass sequent green traffic lights by traveling at a constant speed (within a degree of error in reality). This means that the traffic system can easily be corresponded with the speed of the car. The only thing for this system that we need to know, is what the speed limit should be of the road it’s traveling on. For instance when the speed limit is 60 km/h, and one has just past a green traffic light, and the next one is appearing in about 1 kilometer, then the next traffic light should turn green one minute after the previous one has turned green. This time is set that way because within this time, assuming a car will drive with a speed equal to the speed limit, then it will cover that one kilometer in one minute as well. This way, when the car is driving at a constant speed, it can always pass a green light. This is all because the moment the next light turns green, is slightly earlier (due to accelerating from 0 to the speed limit) then the moment where the car arrives at the traffic light. This way the car can drive further without pressing the brakes to slow down. This now introduced traffic system, will be crossed with the traffic system made by the previous groups. So on one hand, at the intersections the main focus is to give advantage to the longest row of vehicles. This whilst a green wave is being forced through the ring, so this green wave has a priority on the intersection system when it is about to pass through an intersection. This means that an alternate cost function needs to implement green waves as well.

New Cost Function

The new cost function looks a lot like the old cost function but works quite different. The new cost function for a car lane is update to implement the new “clock”. Well the function for calculating the cost for pedestrains stayed the same. The new function for a car lane is:

  • Cost_Lane = Cost_traffic + Cost_waittime + Cost_waitlimit = A^T(t) + C_1 * t + P * e_1(t):

And for the pedestrians:

  • Cost_Pedestrianlane = Cost_waittime + Cost_waitlimit = C_2 * t + P * e_2(t);

Here are:

  • C(t,A): The total cost dependent off of the amount of cars in a row and the waiting time of the car who has to wait the longest at the intersection to cross it.;
  • A: The total amount of cars in an intersection row;
  • T(t): A function that shows whether a row is in a green wave, and where;
  • C_1: The constant to provide the severity of the waiting time in front of a traffic light;
  • t: The waiting time;
  • P: A large value (in the order of thousands);
  • e_1(t): A function switching to 0 if t < T_maxcar and to 1 if t > T_maxcar;
    • T_maxcar: the maximum time a vehicle can be expected to wait at a intersection;
  • e_2(t): A function switching to 0 if t < T_maxpedestrian and to 1 if t > T_maxpedestrian;
    • T_maxpedestrian: the maximum time a pedestrian can be expected to wait at a intersection;

In this function it is implemented that a light is turned green earlier when a row at an intersection is in a green wave.

As stated and defined above, a new cost function is presented to create the traffic algorithm. As one can see, there are a few differences. First of all N + B is being replaced with just a regular capital A, which stands for the total amount of cars (assuming that these are all man-driven). The rest of the constants that were already in the cost function made by group PRE2016 1 group 2 are still in the formula. A major difference however is the function T(t). This function provides to which the total amount of cars in a row at an intersection is put. Note that this function is always greater or equal to 1. This function behaves like a tent when the row is in a green wave (generated as a traveling signal through the total traffic system). When the green wave begin with its passing by the value starts to rise. It reaches its peak at the middle of the green wave signal (the green wave signal and the system is explained in the part about thew simulation). After the middle of the signal has passed, the values of the function start to linearly drop to 1. So now, when a green wave passes by, it has to seem, to the traffic light, that there are a lot of cars waiting to cross the street. This will have the traffic system which throughputs the green wave, give a priority on crossing in relativation to the the rows which have a relatively fewer amount of cars waiting. After all, the traffic light with the highest cost of all of the lights in the intersection, turns green first (as created by the past group). Depending on how big the value of C_1 is, the waiting time of the cars will also be weighed in the cost function. When this value is made larger, priority is given to the row which has the cars that are waiting the longest. So the weight will proportionally grow with the implementation of waiting time. P is a large value (like 10000) which will only be put into the cost function, when the longest waiting car in the row had waited for T_maxcar seconds or longer (for pedestrains this is T_maxpedestrain)ohh. This is obviously implemented to prevent one car from waiting too long, when a large amount of cars are on the other roads.

Simulation

To simulate the traffic situation a road plan which will symbolize the “ring of Eindhoven” with a reduced amount of intersections will be simulated. There will be 12 intersections in the simulation to test how the old system will work over several intersections, as well as how our new system compares to the old one. A simulation was made in netlogo to figure out the different systems compare to one another. Netlogo was chosen since it is a modeling environment which can be programmed in lots of different ways. The netlogo program also has the behaviorspace module which can be used to simulate a written program with different settings. This came in useful in testing for which settings our system is the biggest improvement to the old one.

Program description

GUI of the new program

There are a few things that can be changed in the simulation. Before the simulation is set up, one can change the distribution of the directions from spawn by using the RealDistribution button. The amount and power of the clock hands can also be changed before setup. The speed of the clock and the amount of cars on the road can be manipulated during the simulation. The amount of ticks that will be run can be set in the runfor box. A car can also be spawned on the ring to investigate how a car driving a full circle on the ring is affected by the systems. It is also possible to run the simulation for one tick with the button GoOneTick. Setup sets up the simulation and its variables, after which go can be used to start and stop the simulation. The last button of interest is a button to export the data to a csv file. It will be output to a file named 1Clocks(clocamount)Power(clockpower).csv with (clockamount) being the amount of clocks set in the silder and (clockpower) being its power set in the slider. If the file name exists the number in front of the name will be incremented by one, up until 10, after which a message is printed to the command center warning that the data was not exported. The data that is of importance to the model is displayed in the box in the top left of the screen. The simulation can also be viewed, the first intersection is shown in screen on setup, and the other intersections can be seen when the simulation is scrolled of screen.

Outputs

As outputs on the simulation a few values are important:

  • Cars that got to their destination
  • Average speed of cars
  • Average times stopped per car
  • Average time stopped per stop
  • Average time stopped per car
  • Average finish time driven per car

Each of these values were also split between cars just crossing the ring, and thereby not actually driving on the ring itself, and cars that at least move a bit on the ring, since the cars that actually move on the ring should be more affected by the green waves. These outputs are also the ones which are in effect when the data is exported by the export data button.


Testplan

As seen in the ‘’dashboard’’ of the Netlogo program, some of the variables can be changed. The ones that matter the most in our program are focused on the use of the clock algorithm. Clocks are, in our program, expected to deliver positive changes in most of the parameters that can be measured, such as the total time stopped, the amount of cars stopped, the amount of cars on the road etc. In our clock system it is obvious that we needed to factor in two questions: how powerful should a clock be, and how many clocks should be on the ring? For this reason we implemented the following sliders in the program: Clock power and amount of clocks. For the test plan we needed to figure out how to run the program efficiently.

The clock power can be slid between 2 and 4, with a deviation of ½ . These numbers represent the power to which the amount of cars is raised at the start of the green wave. In the middle of the green wave this power will be 1½ times bigger. So the power will be raised from beginning to middle, and will be reduced from middle to end.

The amount of clock signals can be changed between 0 and 10 with a deviation of 1 clock. 0 meaning that there is no influence from green waves on the traffic on the ring, because there is no green wave signal. 10 meaning that 10 of these power function signals are sent through the intersection system, at the same speed as the cars in the program.

For the test plan of this program we decided to run the program as follows:

For 0 green wave signals we measure the parameters in one run. No green wave signal naturally means that there is no need for this amount to run in with different clock powers, because they won’t have effect when there is no green wave signal at all. This allows us to take a partial look into the results the previous group would have gotten, when the traffic lights with their cost function would be chained to more intersections. The rest of the results are obtained through running the program for 100.000 ticks for all remaining possible combinations of clock power with the amount of clocks. So every setting with a clock power between 2 and 4 and the amount can be changed between 1 and 10. This will give us 50 more results (5 power setting, 10 amount settings). The results of these runs are being put in an excel file which hands us the possibility to quickly see the best outcome per measured parameter. together, there are 51 different setting states that are worth exploring into. These are all ran twice. This is due to the random spawning of the cars on the road. By running them twice, we can take the average, so the deviations in spawn rate can be cancelled out a bit. The simulations are also ran with a focus on the parameters concentrating on ‘’cars at least a bit on the ring’’. This means that we exclude cars that just cross the ring from their spawn street to the opposite street.

The simulations with the lowest setting (0 green wave signals and any power) and the highest settings (10 wave signals and a clock power of 4) are being ran with test cars, which drive along the full ring once. These test cars are spawned every 1000 ticks. This is done because we want to obtain specific results for one car as well. We choose for these cars to be spawned after fixed times, so we can make an average, mainly because of the change of states at the intersections.

Results

During the simulation, the results were obtained through running the NetLogo program as described above. The simulation would run for every combination of the clock power and the amount of clocks. Plots and tables for the results were made for the following outputs:

  • Average finishing time
    • Cars traveling a full lap around the ring
    • Cars traveling a part of the ring
    • All cars
  • Average time stopped per car
    • Cars traveling a full lap around the ring
    • Cars traveling a part of the ring
    • All cars
  • Average times stopped per car
    • Cars traveling a full lap around the ring
    • Cars traveling a part of the ring
    • All cars
  • Average time stopped per stop
    • Cars traveling a full lap around the ring
    • Cars traveling a part of the ring
    • All cars
  • Amount of finished cars
    • Cars traveling a full lap around the ring
    • Cars traveling a part of the ring
    • All cars

Some hypotheses were made before looking into these results too much. These are the following:

  • The average stopping time per car would be decreased with the implementation of clocks for all cars. The most cars are on the ring for a bit after all, and therefore should be able to travel more fluently with a working clock signal.
  • The amount of finished cars would be higher. Since we predict a better throughput for more clocks/higher clock power, we expect more cars finishing for every specific time span.
  • A higher clock power is beneficial for the cars traveling a full lap in terms of the finishing time. These cars are supposed to travel along with a green wave. So when the clock power will be higher, we expect these cars to have a priority on the rest of the cars. Which means that we expect these cars to have a shorter finishing time due to traveling longer (in terms of distance) with a green wave.
  • Average time stopped per stop would not differ that much between the cars for different clock powers/amounts. This thought came up because of the supposed fact that a higher clock power/clock amount would result in a bit longer of a waiting time for cars of the side roads. This would result in an increase of the waiting time for cars waiting to get on the ring, which increases the overall average.
  • The average times stopped per car will overall decrease. Most of the cars are supposed to, at least once, travel along the green wave signal, which already means certainly one stop less in comparison to a system without this signal. This would build up since cars will most likely be in a green wave for a longer distance than two intersections.
  • The average times stopped per full lap car will be a bit larger than the average among all cars. This is mainly because of the proposition that these cars will catch more green wave signals and thus very likely will travel more with a green wave. This will result in not very many stops.

The output data, such as the finishing time, time stopped etc. were put automatically into an Excel file, after the simulation had stopped for a certain amount of ticks (in our case 100.000). From this file, a proper analysis of the trends that were occurring was done. From this Excel file, it was possible to make some graphs as well. This would be more meaningful for analysing the results because a visual of the results is easier and more comfortable to work with than a table with hundreds of numbers.

The whole table of the results is referenced in this link

The plots for these results are also put in a file.

As a leap towards the analysis: the plots show decreasing trends which is something that we predicted for some of the outputs. In the analysis, short versions of the tables, so tables with less but more significant and important results, are presented and discussed.


Analysis

Now that some results have been gathered, some analysis can be done to see whether the implementation of a new system has improved in some sort of way. For this, the several different aspects will be judged, as written in section 3:

  • The throughput of the system: How many cars pass the system within a set amount of time
  • How often a car has to stop during their trip
  • How long a car has to stop on average for all cars
  • How long a car has to stop when stopped
  • The average time it takes for an individual to drive to its destination

The results can be split into several different categories before looking into the different evaluation aspects. These categories are: all cars, the cars making one full lap on the ring and the cars who travel along the ring at least one intersection. After this, there can also be made the difference between the clock powers ranging from 2 until 4. To begin with, the best clock power and amount will be determined, after which the most improved category will be determined, all of which are based on the five aspects.

Clock power and amount

First the optimal clock amount will be determined. For this, the difference in the aspects will be checked, generally speaking. Doing this, the following can be concluded:

  • The average time it takes for an individual to drive to its destination seems to be less when adding more clocks, while the clock power does not seem to have a direct impact.
  • The average time a car stopped also decreases as more clocks are added, and the clock power seems to help this decrease as well, but not as substantial of an impact as the addition of more clocks.
  • The average time stopped per stop seems to be increased or decreased as more clocks are added, and even more with a higher clock power, depending on which category is being looked into.
  • The average time a car had to stop, however, overall decreases as more clocks are added and does not seem to depend on the power of the clocks.
  • The amount of cars that pass through the system seems to be slightly decreased as more clocks are added, while the power of the clock does not have an influence.

Thus the final conclusion is that more clocks is better, generally speaking, while more power does not influence it negatively (but not always positively either). As the power of the clock is not of a substantial influence on all aspects, aside from how much time a car spends stopped and the average time it stops per stop, it suffices to just look at the average of all clock powers with highest amount of clocks, as will give a more accurate depiction of how the results actually vary between systems.

Most improved category

In this section, the three categories will be looked into individually to see which one has been influenced the most by the new system. All of the data can be summarised in the next tables:

Table 1: Summarised results
All cars Cars a bit on the ring Cars going a full lap
Clocks 0 10 Difference (%)
Cars that finished 87071,4 86697,6 -0,429
Average times stopped per car 0,6922164 0,656613 -5,143
Average time stopped per stop 151,2183286 156,2851091 3,351
Average time stopped per car 105,8954501 104,0837588 -1,711
Average finish time 1122,56263 1112,6247334 -0,885
Clocks 0 10 Difference (%)
Cars that finished 51933,4 51636,2 -0,572
Average times stopped per car 0,8982215 0,8500527 -5,363
Average time stopped per stop 150,2130625 150,7533405 0,360
Average time stopped per car 137,5629334 131,2303453 -4,603
Average finish time 1709,580975 1685,214118 -1,425
Clocks 0 10 Difference (%)
Cars that finished 94 93,4 -0,638
Average times stopped per car 8,0702127 6,5082446 -19,355
Average time stopped per stop 107,2291591 95,9187199 -10,548
Average time stopped per car 865,4702127 625,5409332 -27,838
Average finish time 5732,030851 5478,009623 -4,432


As can be seen in the tables, the average times stopped per car is decreased by at least 5.1% in all of the cases, and by 19.4% when looking only at cars that go one full lap. This seems to be the largest difference on average between the two clocks, while the smallest is the amount of cars that finished, being around a 0.4% to 0.6% decrease in the three cases. The most interesting of the criteria most certainly is the average time stopped per stop. For all cars, this is an increase of around 3.3%, for cars that travel along at least one intersection it is an increase of around 0.4%, while for cars going a full lap it is a decrease of 10.5%. This means that if you travel along the ring, you will experience less time stopping each time you have to stop. This is also noticeable via the average time stopped per car, as this is decreased by 27% if you travel one full lap, and by 4.6% if you only travel a little bit. The travel time decreases by around 4.4% for a full lap and decreasing to 1.4% if taking a part of the lap. These results can be compared to real life situations in the following way: there is a substantial decrease in the amount of time spent on the lap or distance in general, if you travel along the ring for long enough, while the cars that do not travel there, do not experience much hinderance. Besides this, there is also a decrease in stops that someone has to perform during the trip.

Conclusion

Influence on USE- aspects

As we saw in the results that the total travel of all the cars are not affected by the green waves. So the main user aspect (fast to destination) is not realised. However it can be seen that there are 5% less cars that come to a full stop. This results in a more convertible ride , as well as less energy consumption and CO2 emission . Since acceleration is more energy demanding than driving at a contrant speed. This brings us to a improvement of the Society since their main goals where the create a greener environment, with less pollution. As well as not spending too much money on it. This is also true since we do not use expensive ways to communicate with cars. At the end The enterprise is not affected by green wave technologie. Since traffic systems do not have the option to communicate with cars in the model that was created. Therefore car manufacturers have no need to build a communication system in the cars.

Improvements when compared to the old system

As seen in the analysis of the results, the new system makes an improvement in all the different aspects that were looked into, when driving alongside the ring for at least some distance. This means that the new system is better generally speaking, while not causing substantial problems for the traffic that does not travel on the ring long enough to experience all of the perks.

Discussion

As we saw in the conclusion green waves help to lower the pollution of cars in the city's. But how trustworthy was our model ? Are there things that can be added to the model to make it more realistic ? Are there models that may be more efficient using more advanced technologies ? What was changed in the model during the program and why did it change? These are the questions that will be discussed in this section.


To start with the last question: What was changed in the model during the program and why did it change?

At the start of the project we wanted to make a model that showed us the effect autonomous cars have on the traffic system. But after a while we came to the conclusion that this was too complex. So we decided to narrow our reaches down to what are the effects of platoons which are formed by autonomous cars, and what fraction of the autonomous cars is needed to make the platoon effective. A week later it was we came to the conclusion that platoon’s where too complex and that autonomous cars were also a little too complex. After this decision we decided to only focus on smart green waves on a city ring road.

Are there things that can be added to the model to make it more realistic ?

In order to simulate the model assumptions were made to make the model programmable. However these assumptions also make the model a little less realistic. For instance the choice was made that we do not include emergency vehicles in our model. Looking back at the program it may was possible to integrate this in the cost function, but on the other hand the change that a emergency vehicle drive over a crossing point is less than 0.1% this is the reason to not put so much effort in implementing the emergency vehicles in the model.

There is also an assumption that probably made the model less realistic. In the model every car has the same driving properties. They may have different destinations but there are no tailgaters , hogs or slow old grandmas on the our model. Another point is that that there is no difference in car types , brands or models. A full electric car has no CO2 emission where most old timers do not even have a filter on there exhausts, so different cars have different pollution rates .

It may be possible to integrate by giving every car a different acceleration , reaction time , maxspeed , social drive level and pollution rate parameter. Those parameters are picked from some distribution (could be binomial , normal , exponential or even chisquare). However one downside is that is a lot to program and it asks a lot of the memory of the computer, with will result in much longer run time the simulation.

Are there models that may be more efficient using more advanced technologies ?

As discussed in the literary study new evolving technologie can give the traffic system way more data through sensors as well ar through communication with autonomous cars. If the traffic system has this data a cost function can be more specifically defined. For instance if a car has a higher amount of CO2 emission when accelerating. It may be an idea to give this cars more value in the cost function.

References

  1. Sterbentz, J., “Valencia Signals Re-timed to Improve Traffic Flow and Safety”, Streetsblok SF, 2-3-2009. Available at: http://sf.streetsblog.org/2009/03/02/valencia-signals-re-timed-to-improve-traffic-flow-and-safety/
  2. Author unknown, “Drivers catch green lights 'wave'”, BBC News, 14-4-2009. Available at: http://news.bbc.co.uk/2/hi/uk_news/7998182.stm
  3. Jae-Hoon J., Min K. and Gi-Sig, B. “Position recognition for an autonomous vehicle based on vehicle-to-led infrastructure”, Lecture Notes in Electrical Engineering, Vol 415 LNEE, 2017, p.p. 913-921.
  4. Hayama, K. and Minakata, T. “A far infrared vehicle sensor for a traffic signal control”, 15th World Congress on Intelligent Transport Systems and ITS America Annual Meeting 2008, 2008, Vol 1, p.p. 99-104
  5. 5.0 5.1 5.2 Lambert, F., "A look at Tesla’s new Autopilot hardware suite: 8 cameras, 1 radar, ultrasonics & new supercomputer", 2016, Available at: https://electrek.co/2016/10/20/tesla-new-autopilot-hardware-suite-camera-nvidia-tesla-vision/
  6. Author unknown, "Hardware voor volledig zelfrijdende besturing in alle auto's", date unknown, Available at: https://www.tesla.com/nl_NL/autopilot?redirect=no

Planning and project information

In the beginning of the project, we had a certain planning that said what everyone had to do in a specific week. This was abbreviated with letters for the different people. The planning can be seen in table 1.

Table 1: Initial planning
week 3 week 4 week 5 week 6 week 7 week 8
Understanding the current traffic system All All
The effects of autonomous vehicles on the traffic system K M T F T
What makes an autonomous vehicle better in traffic S F L S L
How are humans in the traffic affected S F L S L S L
What can be changed to optimise traffic with autonomous vehicles K M T M T M T
Model of the new traffic system K F K F K F K F
Complete the article All All
Work on final presentation ? All

After a couple of weeks, there were some complications, and certain deadlines were not met. Because of this, and the fact that our initial approach turned out to be wrong, we changed our entire planning so that we could still finish the project in time and have time remaining to give some finishing touches. This can be seen in table 2.

Table 2: Eventual planning
25-3 27-3 30-3 2-4 4-4 5-4 8-4 10-4 13-4
Programming in Netlogo T K T K T K T K
Rewriting focus, objectives, approach F S F S T K
Literature study green waves, platooning, sensors vs chips, autonomous cars M L M L L F
Results of program L K T L K T L K T L K T
Testplan L K T
Final presentation S M L M L
Description old system T T
Description new system K K K
Peer-review All All All All All
How the program works T T
Description clock system S
Influence on the USE aspects F
Analysis of results and conclusion M M M M
Writing discussion F F F
Rewriting introduction S
Finalisation All

Because everyone writes their own parts, it still needs to be updated to the wiki. This has been delegated to Matthijs, while the final checker of for example grammar mistakes and of the wiki itself, has been delegated to Lars.

As part of the task division, there were not really special tasks that were given to certain people; everyone did their part of the project. There is however a small difference in the way people acted during meetings, or how they performed in the group itself.