Integration Project Systems and Control 2013 Group 3: Difference between revisions
Jump to navigation
Jump to search
Line 126: | Line 126: | ||
| - FRF will be used to obtain a model of the system. This method can be used to obtain a model of a system without knowing all the parameters of the system. | | - FRF will be used to obtain a model of the system. This method can be used to obtain a model of a system without knowing all the parameters of the system. | ||
|- | |- | ||
| | | ''Assumptions: | ||
|- | |- | ||
| - Initially a PID controller will be used to follow the set trajectory. A PID controller will be used because it is a simple controller and every team member is familiar with the concept. To increase performance this PID controller can be extended with feedforward. When this controller functions according to the set requirements, different control methods will be explored to investigate if it would be possible to increase performance. '' | | - Initially a PID controller will be used to follow the set trajectory. A PID controller will be used because it is a simple controller and every team member is familiar with the concept. To increase performance this PID controller can be extended with feedforward. When this controller functions according to the set requirements, different control methods will be explored to investigate if it would be possible to increase performance. '' |
Revision as of 22:56, 25 February 2013
Group Members
Name: | Student id: | Email: |
Joep Alleleijn | 0760626 | j.h.h.m.alleleijn@student.tue.nl |
E. Romero Sahagun | 0827538 | e.romero.sahagun@student.tue.nl |
M. Kabacinski | 0789360 | m.j.kabacinski@student.tue.nl |
N. Kontaras | 0827208 | n.kontaras@student.tue.nl |
A. Simon | 0676675 | a.s.simon@student.tue.nl |
Planning
Week: | Activities: | |
---|---|---|
Feb 18 - Feb 24 | ||
- Make a list for the requirements of the controller | ||
- Prepare and conduct tests for coupling/decoupling(JA,NK,MK) 3.5 hours | ||
- Prepare and conduct tests for non linearity (JA,NK,MK) 3.5 hours | ||
- Prepare and conduct tests for joint identification and create FRF models of the joints (JA,NK,MK) 5 hours | ||
- Set up DH transfer matrices (AS) 5 hours | ||
- Generate Matlab Simulation of the kinematic chain (ER) 7 Hours | ||
Feb 25 - Mar 3 | ||
- Design PID feedback controller, add feedforward and test on the robot for each joint (JA,NK,MK) 11 hours | ||
- Prepare testing procedure (JA,NK,MK) 1.5 hours | ||
- Implement inverse kinematics (IK) code in matlab (AS) 2 hours | ||
- Matlab code for trajectory generation (TG) (ER) 5 hours | ||
Mar 4 - Mar 11 | ||
- Test controllers on the robot (JA,NK,MK) 2 hours | ||
- Test trajectory generation on the simulation (ER) 3 hours | ||
- Integrate Inverse Kinematics with Controllers (AS,ER) 2 hours | ||
Mar 12 - Mar 19 | ||
- Consider different controller design methods (JA,NK,MK,AS,ER) 10 hours | ||
- Work on report (JA,NK,MK,AS,ER) 2 hours | ||
Mar 20 - Mar 27 | ||
- Test routine generation on the robot (JA,NK,MK,AS,ER) 2 hours | ||
- Select optimal routine (JA,NK,MK,AS,ER) 4 hours | ||
- Problem solving (JA,NK,MK,AS,ER) 10 hours | ||
- Consider different controller design methods (JA,NK,MK,AS,ER) 10 hours | ||
- Test different controllers (JA,NK,MK,AS,ER) 5 hours | ||
- Work on report (JA,NK,MK,AS,ER) 2 hours | ||
Mar 28 - Apr 4 | ||
- Work on report (JA,NK,MK,AS,ER) 15 hours | ||
- Prepare presentation (JA,NK,MK,AS,ER) 5 hours |
Progress
Week 1: Feb 18 - Feb 24
Week 2
- ...