PRE2015 3 Groep2: Difference between revisions
Jump to navigation
Jump to search
Line 41: | Line 41: | ||
[http://cstwiki.wtb.tue.nl/index.php?title=PRE2015_3_Groep2_week3 Week 3: Redefining focus and deliverables and starting research ] | [http://cstwiki.wtb.tue.nl/index.php?title=PRE2015_3_Groep2_week3 Week 3: Redefining focus and deliverables and starting research ] | ||
[http://cstwiki.wtb.tue.nl/index.php?title=PRE2015_3_Groep2_week4 Week 4: Name yet to be determined... ] | |||
== Project Planning == | == Project Planning == |
Revision as of 11:43, 29 February 2016
Delivery Drones
Group Members
Student | Student number | |
---|---|---|
Stevie van der Loo | 0813076 | Logbook |
Elbert van de Put | 0897289 | Logbook |
Jeroen Setz | 0843356 | Logbook |
Marijn Tibboel | 0909136 | Logbook |
Maarten Vlaswinkel | 0899061 | Logbook |
Mert Zararsiz | 0865084 | Logbook |
Project Progress
Week 3: Redefining focus and deliverables and starting research
Week 4: Name yet to be determined...
Project Planning
Week 2
- Laws for drones → Martijn
- Planning → Jeroen
- Presentation on Monday → Martijn, Elbert, Jeroen
- Explaining focus and new scenario → Jeroen
- Start Navigation → Maarten, Elbert
- Start Verification → Mert, Stevie
- If anyone is done, they can help extending navigation or verification
Week3
- Locating and maneuvering the drone
- Verification of the costumer
- Finishing the focus and requirements
Week 4 (start test-phase)
- Navigation, Verification (try to finish the protocol/theory)
- Starting the practice (controller)
Week 5 (test-phase)
- Practice feedback
- Research (and if possible implement) improvements
Week 6 (test-phase)
- Implement improvements
- Documentation
Week 7 (finishing test-phase)
- Finishing practice + documentation
- Final report
Week 8
- Finishing Report