| Line 32: | Line 32: | ||
| |4 hours | |4 hours | ||
| |- | |- | ||
| |06-12-2015 | |||
| |Simon | |||
| |Working on the top level simulation | |||
| |6 hours | |||
| |} | |} | ||
Revision as of 17:56, 6 December 2015
Back to: PRE2015_2_Groep1
| Date: | Student(s): | Task: | Hours spend: | 
| 30-11-2015 | Jesse, Alex, Simon and Guus | Making a specific planning for the rest of the case and tried to find Harry van de Loo in order to ask about the availability of the mindstorm robots. | 2 hours each (=8 hours total) | 
| 30-11-2015 | Simon | Working on the first simulation (top level) | 3 hours | 
| 04-12-2015 | Jesse, Alex, Guus | Aquiring of the robot parts and the assembly of the robot swarm | 5 hours each (=15 hours total) | 
| 05-12-2015 | Simon | Analysing the texts from [Liu B Chen P Wang G], [Qi G Song P Li K] and [Nicolis S Detrain C Demolin D Deneubourg J] to compose a swarm algorithm for the top level simulation. Also work on the simulation itself. | 3 hours | 
| 06-12-2015 | Jesse | Finding out how the RCX 2.0 bricks can be programmed and write a first script to run on for the Lego Mindstorms Robots | 4 hours | 
| 06-12-2015 | Simon | Working on the top level simulation | 6 hours |