Line 62: | Line 62: | ||
| 13-Sep | | 13-Sep | ||
| 3 | | 3 | ||
| Problem definition | | Problem definition | ||
| | | Wrote the problem definition. | ||
|- | |- | ||
| 15-Sep | | 15-Sep | ||
Line 72: | Line 72: | ||
<br> | <br> | ||
'''Total hours:''' 13 hours | '''Total hours:''' 13 hours | ||
= Week 3 = | |||
{| border="1" class="wikitable" | |||
|- | |||
! width = "10%" | Date | |||
! width = "5%" | Time Spent | |||
! width = "20%" | Task | |||
| width = "50%" | Description | |||
|- | |||
| 16-Sep | |||
| 3 | |||
| Product requirements | |||
| Looked up what product requirements were & then wrote some that would be suitable for the mailbox | |||
|- | |||
| 18-Sep | |||
| 4 | |||
| Group meeting | |||
| Brainstormed various components & full ideas of mailboxes; also made an action plan for Monday. | |||
|- | |||
| 20-Sep | |||
| 5 | |||
| Concepts | |||
| Made sketches in Powerpoint and uploaded them with some explanation. | |||
|- | |||
| 21-Sep | |||
| 1 | |||
| Remaining concepts | |||
| Made remaining sketches in Powerpoint and uploaded them with some explanation. | |||
|- | |||
| 22-Sep | |||
| 2 | |||
| Group meeting | |||
| Discussed plan of action for the upcoming weeks. Task division. And picked out our 3 main concepts to get fully on paper and possibly 1 tested. | |||
|- | |||
| 22-Sep | |||
| 1 | |||
| Mentor meeting | |||
| Mentor looked at how far we have come in the wiki and discussed our further plan of action; we also received a deadline for next week which is: all new wiki pages print. | |||
|} | |||
<br> | |||
'''Total hours:''' 16 hours | |||
= Week 4 = | |||
{| border="1" class="wikitable" | |||
|- | |||
! width = "10%" | Date | |||
! width = "5%" | Time Spent | |||
! width = "20%" | Task | |||
| width = "50%" | Description | |||
|- | |||
| 16-Sep | |||
| 3 | |||
| Product requirements | |||
| Looked up what product requirements were & then wrote some that would be suitable for the mailbox | |||
|- | |||
| 18-Sep | |||
| 4 | |||
| Group meeting | |||
| Brainstormed various components & full ideas of mailboxes; also made an action plan for Monday. | |||
|- | |||
| 20-Sep | |||
| 5 | |||
| Concepts | |||
| Made sketches in Powerpoint and uploaded them with some explanation. | |||
|- | |||
| 21-Sep | |||
| 1 | |||
| Remaining concepts | |||
| Made remaining sketches in Powerpoint and uploaded them with some explanation. | |||
|- | |||
| 22-Sep | |||
| 2 | |||
| Group meeting | |||
| Discussed plan of action for the upcoming weeks. Task division. And picked out our 3 main concepts to get fully on paper and possibly 1 tested. | |||
|- | |||
| 22-Sep | |||
| 1 | |||
| Mentor meeting | |||
| Mentor looked at how far we have come in the wiki and discussed our further plan of action; we also received a deadline for next week which is: all new wiki pages print. | |||
|} | |||
<br> | |||
'''Total hours:''' 16 hours |
Revision as of 10:01, 17 October 2014
Go back to Personal Logs.
Week 1
Date | Time Spent | Task | Description |
---|---|---|---|
01-Sep | 2 | 1st Class | Brainstorm Project Ideas |
02-Sep | 2 | Research | Did some research on Amazon Prime Air. |
04-Sep | 2 | Group Meeting | Discussed our topic and research tasks & presentation were divided |
06-Sep | 2 | Presentation preparation | Made the first presentation. |
08-Sep | 2 | Lecture | Listened to group presentations of their projects & approaches. Presented our own idea. |
Total hours: 10 hours
Week 2
Date | Time Spent | Task | Description |
---|---|---|---|
09-Sep | 2 | Research | Searched for literature on Amazon Prime Air. Could not find enough. Concluded we had to change our project plan. |
11-Sep | 4 | Group meeting | Discussed our topic/whether or not we needed a new one & divided task |
12-Sep | 2 | Planning | Made the planning. |
13-Sep | 3 | Problem definition | Wrote the problem definition. |
15-Sep | 2 | Lecture | Listened to renewed group presentations of their projects & approaches |
Total hours: 13 hours
Week 3
Date | Time Spent | Task | Description |
---|---|---|---|
16-Sep | 3 | Product requirements | Looked up what product requirements were & then wrote some that would be suitable for the mailbox |
18-Sep | 4 | Group meeting | Brainstormed various components & full ideas of mailboxes; also made an action plan for Monday. |
20-Sep | 5 | Concepts | Made sketches in Powerpoint and uploaded them with some explanation. |
21-Sep | 1 | Remaining concepts | Made remaining sketches in Powerpoint and uploaded them with some explanation. |
22-Sep | 2 | Group meeting | Discussed plan of action for the upcoming weeks. Task division. And picked out our 3 main concepts to get fully on paper and possibly 1 tested. |
22-Sep | 1 | Mentor meeting | Mentor looked at how far we have come in the wiki and discussed our further plan of action; we also received a deadline for next week which is: all new wiki pages print. |
Total hours: 16 hours
Week 4
Date | Time Spent | Task | Description |
---|---|---|---|
16-Sep | 3 | Product requirements | Looked up what product requirements were & then wrote some that would be suitable for the mailbox |
18-Sep | 4 | Group meeting | Brainstormed various components & full ideas of mailboxes; also made an action plan for Monday. |
20-Sep | 5 | Concepts | Made sketches in Powerpoint and uploaded them with some explanation. |
21-Sep | 1 | Remaining concepts | Made remaining sketches in Powerpoint and uploaded them with some explanation. |
22-Sep | 2 | Group meeting | Discussed plan of action for the upcoming weeks. Task division. And picked out our 3 main concepts to get fully on paper and possibly 1 tested. |
22-Sep | 1 | Mentor meeting | Mentor looked at how far we have come in the wiki and discussed our further plan of action; we also received a deadline for next week which is: all new wiki pages print. |
Total hours: 16 hours